Long-delayed £80m A46 bridge nears completion as traffic restrictions lift

Local News by Andy Mitchell - Local Democracy Reporter 26th Nov 2026  
Inflation and redesign work for the bridge saw costs soar with an overall budget of £80 million set in December 2025 (Image by Nub News)
Inflation and redesign work for the bridge saw costs soar with an overall budget of £80 million set in December 2025 (Image by Nub News)
advertisement

Warwickshire County Council expects to finally complete work on the A46 'Bridge to Nowhere' near Leamington by the end of February.

The revised date is up to six months earlier than the latest target of summer 2027 but still four-and-a-half years later than the original opening date of summer 2022.

The original project for a new, additional bridge over the A46 at Stoneleigh Junction was brought forward to add capacity and improve road safety in the area but it was hit by extensive delays with contractors Colas unable to source vital materials.

That led to lengthy disagreements with the council over who was responsible while the unconnected bridge towered over one of Warwickshire's busiest arterial routes, being passed by thousands of frustrated road users day after day.

Inflation and redesign work saw costs soar with an overall budget of £80 million set in December 2025 – more than double the original estimate of £38 million with the council on the hook for all of the cost overruns.

But an update to the communities overview and scrutiny panel this week, delivered by the council's director of infrastructure, planning and environment Steve Smith, finally brought better news.

"The latest programme has improved," he said.

"The contractor is looking to bring forward the completion as much as possible and progress has been good over 2026, helped by the weather.

advertisement

"Their latest programme shows completion towards the end of February. They are ahead of that programme still, let's hope that the winter months are kind.

"They have some concreting work on the deck that approaches the bridge and then the tarmac surface on the bridge and approaches, they are the major exercises still left to do over the coming months but everything looks good for what I hope to be completion by the end of February.

"We will keep members up to date the closer we get."

No update was provided on whether all of the extra budget will be required.

Scrutiny chair Councillor Jan Matecki (Con, Budbrooke & Bishop's Tachbrook), the political lead on this project until Reform UK took charge of the council in May 2025, asked when the lane restrictions, which bring the speed limit down to 50 miles per hour either side of that bridge, would be lifted.

"Residents and motorists from outside Warwickshire have had to put up with this for many, many years now," he said.

"A lot of residents say there is not anybody working in the road, the work is being done to the side walls, and they wonder why the restrictions are still there."

Mr Smith replied: "The parapets that run along the wing walls, there are operatives there next to the carriageway.

advertisement

"One lane is closed both northbound and southbound but we are expecting traffic management to be off by the end of January, once they have cast those parapets."

Download our Nub News App: - It’s FREE and available now
- Breaking news notifications
- Your Town in Your Pocket

Share:

Comments (0)

Post comment

No comments yet!


Downdload our Nub News App:
- It’s FREE and available now
- Breaking news notifications
- Your Town in Your Pocket