HS2 works to begin in Cubbington area in February 2026

By Nadia Sayed   16th Jan 2026

HS2 works begin in Cubbington on February 2, 2026, affecting B4453 Rugby Road (image via WDC)
HS2 works begin in Cubbington on February 2, 2026, affecting B4453 Rugby Road (image via WDC)

HS2 works are set to take place in Cubbington starting next month (2 February).

Works are planned on B4453 Rugby Road, Cubbington and will be split into two phases.

During phase one, a new access will be built for a local business. During phase two, utility connections for BT and Severn Trent Water will be completed.

Phase one will take place from Monday 2 February to Saturday 21 February 2026 and will require a full road closure while a new access is constructed for a local business.

Phase two is scheduled for Monday 27 April to Friday 1 May 2026.

During this phase, temporary traffic lights will be in operation overnight and at weekends to allow utility connection works for BT and Severn Trent Water to be completed.

Access for pedestrians and cyclists will be maintained throughout the works, and a fully signed diversion route will be in place for drivers.

For more updates visit here.

HS2 works are set to take place in Cubbington starting next month (2 February) (image via HS2)

     

CHECK OUT OUR Jobs Section HERE!
leamington vacancies updated hourly!
Click here to see more: leamington jobs

Share:

Comments (0)

Post comment

No comments yet!


Sign-up for our FREE newsletter...

We want to provide leamington with more and more clickbait-free news.